Approval of the Electricity Supply Business Plan.
MSME Information Details
Parameter: All
Authority: Minister/Head of Agency
Requirements
- Business Plan Documents for Electricity Supply
- Introduction;
- Strategy for the development of electricity distribution systems;
- Conditions of the Electricity Distribution Business;
- Electricity Distribution Business Plan;
- Investment requirements and funding indications; and
- Risk analysis.
- Duration: -
- For Electricity Sales Business
- Introduction;
- Strategy for electricity sales;
- Conditions of the electricity sales business;
- Electricity sales business plan;
- Investment requirements and funding indications; and
- Risk analysis.
- Duration: -
- Application for Approval of RUPTL Proposal, containing:
- Projection of Average Growth of Demand;
- Total Planned Development of Power Plants;
- End-of-Year Power Generation Mix Target;
- Total Planned Transmission Network Development;
- Total Planned Substation Development;
- Total Planned Distribution Network Development;
- Total Planned Distribution Substation Development;
- Total Investment Requirements.
- Duration: -
- For Integrated Electricity Supply Business
- Introduction;
- Infrastructure development strategy for electricity supply and sales;
- Availability of energy sources and utilization strategy;
- Conditions of the electricity supply business;
- Electricity supply plan, including:
- Sales Projections;
- Customer Projections;
- Generation (power balance, energy mix, fuel, GHG emissions);
- Transmission;
- Substations; and
- Distribution System.
- Investment requirements and funding indications; and
- Risk analysis.
- Duration: -
Obligations
- Electricity Business Entities must submit a realization report of RUPTL to:
- The Minister through the Directorate General, for Business Entities whose IUPTL is issued by the Minister; or
- The Governor, for Business Entities whose IUPTL is issued by the Governor.
- Duration: -
- Electricity Business Entities holding a Business Territory must implement the approved RUPTL to meet electricity needs within their Business Territory.
- Duration: -
- Electricity Business Entities holding a business territory must amend the RUPTL if there is an order from the Minister or the Governor in accordance with their authority.
- Duration: -
- The RUPTL is evaluated periodically every 1 (one) year by Business Entities holding a business territory. If changes to the RUPTL are required, Business Entities must apply for approval to the Minister or the Governor in accordance with their authority.
- Duration: -
- Any changes to the RUPTL must be approved by the Minister or the Governor in accordance with their authority.
- Duration: -
- Business Entities whose IUPTL is issued by the Governor must submit a copy of the approved RUPTL to the Minister through the Directorate General.
- Duration: -
Sector: Energy and Mineral Resources.
Status: Available
Belongs to:
35114
Need advice on setting up a company in Indonesia?
KBLI.co.id is a subsidiary of Emerhub, the largest independet corporate advisory firm in Indonesia.

Schedule a free consultation
Share your plans for Indonesia with us, and our advisors will recommend the most appropriate type and classification of legal entity for your needs.

No commitment required
We recognize that you might be in the exploratory phase of deciding whether and how to expand into Indonesia. Allow us to simplify this process for you.

Always credible information
Due to frequent changes in regulations and government policies, there is a prevalence of misleading and outdated advice. As we handle company registrations daily, we are well-informed about the most current information.